Anticipated ScheduleThis schedule is based on when tasks are completed or when documents are initially submitted to review agencies. Final approval dates cannot be controlled or guaranteed.

Phase 1- Site Planning & Conceptual

  • Commence April 2026
  • Submittal or Completion September 2026

Phase 2-Rezoning

  • Commence August 2026
  • Submittal or Completion December 2026

Phase 3-Site Construction Documents & Permits

  • Commence December 2026
  • Submittal or Completion May 2027

Phase 4- Building Construction Documents & Permits

  • Commence December 2026
  • Submittal or Completion June 2027

Phase 5-Construction

  • Commence June 2027
  • Completion